Network Working Group Elmer B. Shapiro Request for Comment: 4 Stanford Research Institute Category: Informational 24 March 1969 Network Timetable 1 (n10) network checkout 2 Installation of communcation gear 8/1/69 2a From AT&T and/or BBN need dimensional, power and cabling specifications 2b Need to establish SRI desired alternate locations so as to determine maximum telco cable lengths 2c Need to establish location and drops on voice coordination circuits 2d Need circuit information on voice drops for tie to intercom system 2e Need to order and install a.c. power (coordinate with 4b) 2f See 16 3 Design and construct host-Imp interface 9/1/69 3a Need specifications from BBN 3b Develop trial design 3c Review with system programmers 3d Establish final design 3e Build and design hardware 3f Debug trial software with hardware loop test 4 Imp installation 9/15/69 4a from BBN get dimensional, power and cabling specifications 4b SRI orders and installs a.c. power (coordinate with 2e)